Timeline

of the Estonian Pumped-Hydro Energy Storage
2009

Start of the Development

2009
2012

Project included in the ENTSO-E 10-year network development plan (TYNDP)

2012
2013

Project included in the Projects of Common Interest (PCI)

2013
2016

Paldiski selected as the location
Onshore land rights acquired

2016
2009 - 2018

Strategic environmental assessment (SEA) and Environmental Assessment (EIA) studies

2009 - 2018
2019 - 2021

Geological investigations
FEED

2019 - 2021
2019 - 2022

Permitting

2019 - 2022
2022 - 2024

Arraning financing, revenue certainty and construction tender

2022 - 2024
2025 - 2031

Construction

2025 - 2031
2031

Commissioning

2031

Pealkiri

Lorem ipsum dolor sit amet, consectetur adipiscing elit.

 

Integer efficitur condimentum ipsum, id porta lacus vestibulum et. Aenean quam nisi, consectetur ut feugiat non, dignissim fringilla velit. Etiam vitae dictum dolor. Nullam interdum, neque vehicula accumsan fringilla, orci libero fringilla sem, vel eleifend sapien tortor vel nisi. Ut ornare nibh at gravida vestibulum. Interdum et malesuada fames ac ante ipsum primis in faucibus. Praesent porttitor risus sit amet nisi molestie molestie. Sed lobortis, risus eget elementum mattis, orci neque congue libero, at egestas est purus in massa. Donec at mi condimentum, mollis dolor ut, pellentesque urna. Suspendisse potenti.