We have great news to share – a major milestone has been reached in the realization of Energiasalv world’s first geotechnical pumped storage plant. The environmental impact assessment report of the project has been declared compliant by the Estonian Consumer Protection and Technical Regulatory Authority on 29 of April.
Naturally, the building permit issued to the Project is also the basis for conducting construction procurements. The procurement documentation is being prepared with the aim of finding an EPC contractor, the exact type of contract is still being decided. Tender launch is to be expected in August 2022.
EPC companies are invited to show interest in the Project and its procurement and to ask further questions. The contact point is Ms Meeli Taveter, e-mail meeli.taveter@zeroterrain.com.